Airbus DB2

Project Overview

The expected substantial completion of the Airbus Design-Build Package II Project is scheduled for early May 2020. This project will provide an expansion of the existing Delivery Center with the addition of two aircraft positions, a new Calibration Canopy, new A220 Staging Building, and new parking facilities. Civil Site Infrastructure includes the design of the new aircraft taxiway and apron for the proposed addition of the Delivery Center, parking to accommodate 1200 spaces, and the utilities for the Delivery Center, A220 Staging Building, and the Calibration Canopy. The Delivery Center Expansion is in support of the Airbus plant in Mobile, Alabama, USA for the complete final assembly and delivery of the A220. The project shall be designed and constructed to resemble the existing Delivery Center and with a more customer focused second floor, similar to Hamburg’s Delivery Center. Additionally, the new expansion is oriented 90 degrees to the existing with an additional curved hub space which includes a prominent customer entrance, lobby and multi-purpose space at the first and second level. The multi-purpose spaces shall include a food prep area and designed with the intent to hold ceremonies on both levels overlooking the 5th aircraft bay. The Delivery Center expansion will support two (2) additional bays with an alternate to add bay five (5) located at the northwest corner of the Delivery Center Hub. The intent of the expansion to the Delivery Center is to elevate the client experience, similar to Hamburg’s Delivery Center.

Client

Mobile Airport Authority

Architect

FSB Design, Volkert, Inc.

Project Duration

10 Months

Project Size

  • Delivery Center – 15,000 SF
  • Calibration Hangar/Open Air Hangar – 30,000 SF
  • A220 Staging – 10,000 SF Hangar Door
  • Install 1,200 ST of New Parking Spaces in Multiple Locations

Components

  • Delivery Center Addition of (2) new aircraft positions
  • A220 Staging Building
  • Calibration Hangar
  • 1,200 Parking Spaces
  • LEED v.4 Silver Certification

More Projects

JESCO commercial construction company

RSA Judicial Office Building

This new office building is a twelve-story, 400,000 square foot facility. The building encapsulates the historic Alabama Supreme Court Building. The structure

JESCO industrial construction company

Norbord

This project, located near Guntown, Mississippi, was constructed for Norbord, Inc. Norbord is a world recognized leader in the manufacturing of Oriented

JESCO plant manufacturing engineering

Caterpillar – Oxford

JESCO Design / Build team completed the original design and construction of the 180,000 square feet High Performance Extrusions Plant in July