Thomasville, Alabama
A fully integrated steel pipe manufacturing complex delivered through a multi-phase design-build approach
JESCO provided turnkey design-build services for Lakeside Steel Alabama’s advanced steel pipe manufacturing campus in Thomasville, Alabama, delivering a fully integrated production environment across two major phases. Phase I established a 65,000 SF pipe casing plant featuring clear-span pre-engineered construction, overhead bridge cranes, and critical process equipment installations including an uncoiler, accumulator, and hydrotester. Phase II added a 55,000 SF pipe finishing plant, supporting threading, heat-treating, upsetting, and inspection operations to enable end-to-end steel pipe fabrication on-site. The project also included a 15-acre stone laydown yard and a 700-linear-foot rail spur, with JESCO’s in-house teams handling civil, structural, mechanical, electrical, and equipment installation to create a production-ready facility tailored to Lakeside Steel’s operational goals.

1.5 million SF distribution facility

Floor storage (430,000 SF) & Rack storage (450,000 SF) Employee Amenities Advanced logistics capabilities

Employee Amenities

Advanced logistics capabilities
1.5 million SF distribution facility
Floor storage (430,000 SF) & Rack storage (450,000 SF) Employee Amenities Advanced logistics capabilities
Employee Amenities
Advanced logistics capabilities
65,000 SF pipe casing plant with clear-span construction and overhead cranes
15-acre stone laydown yard and 700-foot rail spur for streamlined material handling
15-acre stone laydown yard and 700-foot rail spur for streamlined material handling

Data Point - Callout - Brief Summary

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Phase I: 12 Months
Phase II: 12 Months
⦁ 120,000 SF total manufacturing space
⦁ 65,000 SF pipe casing plant
⦁ 55,000 SF pipe finishing plant
⦁ Clear-span pre-engineered metal buildings
⦁ Interior equipment pits, trenches, and foundations
⦁ (2) overhead bridge cranes
⦁ Mechanical, electrical, and process system integration
⦁ 15-acre laydown yard
⦁ 700’ rail spur for logistics and shipping
JESCO’s multidisciplinary delivery allowed for simultaneous design and construction of specialized MEP and foundation systems tailored to complex pipe manufacturing processes. Careful planning of the site layout, equipment installation, and logistics infrastructure enabled seamless integration of both phases into one cohesive operation.
JESCO’s self-performed work across key scopes, structure, utilities, and equipment ensured precision, accountability, and speed, providing Lakeside Steel with a high-performance industrial facility built for long-term operational success.
Challenges & Solution
Lorem Ipsum is simply dummy text of the printing and typesetting industry. Lorem Ipsum has been the industry's standard dummy text ever since the 1500s, when an unknown printer took a galley of type and scrambled it to make a type specimen book. It has survived not only five centuries,
Challenges
Solution
Lorem Ipsum is simply dummy text of the printing and typesetting industry. Lorem Ipsum has been the industry's s

It's just been a
pleasure to work with the JESCO team, all the way around.,"

We've been fortunate
enough to work with JESCO and partner up with them. They've been very responsive to our changes. They pick up the phone, they answer, they're quick to respond.,"

We've built a true
partnership with JESCO, we identified that they recognized the quality of our company and our product as an important aspect, and incorporated that into the construction of this concept.,"

What I can say is
working with JESCO, I've never felt that sort of collaboration and team work, and that solutions-oriented type of approach that we have with JESCO.,"